Light stucco and white-sided coastal home with a covered glazed entrance, shallow concrete steps and a sculptural palm.

Free Winter Parking Next to Latham Plaza Is One of the Terms Up for Negotiation

"Parking included as part of the proposed development will not be required to be bound to COJB public parking fee structure." The City of Jacksonville Beach put that sentence in writing on April 23, 2026, in Addendum No. 1 to the solicitation for the city-owned parking lot next to Latham Plaza. In the same answer, the city said it expects development parking to be "subject to negotiation" and that the deal could let the project run "its own parking management and fee structure."

The 2026 paid parking season ended November 1, so the lot between First and Second Streets is back on the off-season schedule downtown regulars know. The redevelopment paperwork shows that schedule is one of the things a future partner can propose to change. The building planned for the site has a firm height cap. The parking rules don't have one.

The Rate Card Proposers Were Invited to Rewrite

The city published RFP 01-2526, "Latham Plaza Parking Lot Public-Private Partnership," on March 18, 2026. The city and its Community Redevelopment Agency are looking for a development team to replace the surface lot with structured parking, public amenities and commercial space. Prospective proposers sent written questions, and many of them were about money from parking.

The city answered them in Addendum No. 2, dated May 18, 2026. One question described the current city rate card as $4 for the first two hours, $2 for each additional hour and a $12 daily maximum. It described the paid calendar as running March through November, with paid hours from Friday evening through Sunday. Here is how the city answered when developers asked about changing each piece:

Parking term City program as described in the RFP questions What the city said proposers may offer
Season March through November Other operating models, including year-round paid parking, for consideration
Days Friday evening through Sunday Weekday paid parking, subject to city review and approval
Rates $4 first two hours, $2 each added hour, $12 daily max Alternative or premium rates for covered parking, which the city has not pre-approved
Fee structure City public parking fees Development parking not required to follow city fees

Each of those answers has conditions attached. According to the city, any change to the paid-parking calendar would need city review, negotiation and possible approval by the appropriate city authority, and it would have to be written into the final project agreement. A weekday paid model would have to address "public access, resident parking treatment, event operations, enforcement, revenue sharing, signage, technology." Any final rate structure would go through negotiation, legal review and approval, and future rate changes would follow the final agreement.

That means the parking terms get settled in the deal itself, and the city has to approve them.

A Height Limit That Counts the Rooftop Bar

The building is the part that can't grow much. The RFP mentions ground-floor retail and restaurants, upper-level commercial space, possibly a rooftop dining venue, wider pedestrian corridors, public art and activity at street level. All of it has to fit under the city's 35-foot height limit.

In Addendum No. 2, the city explained how that limit is measured. Height runs from the crown of the adjacent roadway to the midpoint between the eave and the ridge of the roof. Elevator overruns and mechanical equipment generally don't count. Anything people can occupy does count, including "rooftop dining areas, pergolas, railings, gathering spaces," which have to stay within the 35 feet.

The rooftop restaurant mentioned in the RFP description would therefore sit inside the same envelope as the parking levels and storefronts below it. Proposers can't add height to fit more parking or more commercial space, so how they lay out the floors and what they propose for rates and hours are where the plans can differ.

The 200-Space Floor, and Who Gets Part of It

The city set a minimum. A developer has to replace at least 200 parking spaces. In Addendum No. 2, the city said that figure is "the minimum replacement target, inclusive of staff parking spaces for City employees, for use Monday through Friday 7AM-8PM."

Within that 200, at least 50 spaces are for city use. The city clarified that these 50 are counted inside the replacement total, not added to it, unless a proposer chooses to build more. They are meant for city staff and for anyone doing business at City Hall, Monday through Friday from 7 a.m. to 5 p.m.

Put those numbers together and a minimum build would set aside a quarter of its spaces for city use on weekdays. On weekends and evenings, the full floor of 200 is public replacement parking. Weekday paid hours, which proposers may suggest, would apply mostly to the remaining spaces during those same hours.

What the Surface Lot Brings In Now

The current lot gives a baseline. Addendum No. 1 reports gross revenue of $93,731 for calendar year 2025, not counting app payments, and a vehicle count of 8,226, not counting residential vehicles or Parking.com vehicles.

Since those exclusions apply differently to the revenue and to the vehicle count, the two numbers can't be divided into a per-car average. What they do show is the scale. A full calendar year of charging on the city's March-through-November schedule brought this lot an amount in the tens of thousands of dollars. The RFP asks each proposer for a financing plan covering the city's expected contribution, who owns and operates the parking, a commercial leasing strategy and a schedule. A parking structure that charges more months of the year, or more days of the week, would earn more toward that plan than the surface lot does under today's calendar.

The same addendum says the contract with the city's current parking services operator ended October 31, 2026. Residents who registered for free resident parking in an earlier year stay registered, according to the city's 2026 paid parking announcement, and current rules and payment options are posted on the city's parking page.

Latham Plaza Is on Its Own Budget Track

The plaza is a separate project from the lot. The RFP describes the lot redevelopment as support for "adjacent public investments in Latham Plaza and the Seawalk Pavilion." In Addendum No. 2, the city laid out the plaza's own timeline:

  • Phase I covers the western third of Latham Plaza. Funding is in the fiscal 2026 budget and carries over into fiscal 2027 if it isn't spent.
  • Phase II covers improvements to the rest of the plaza, as approved by City Council. Funding is slated for fiscal 2028.

So the plaza work and the lot redevelopment are on separate timelines, with separate money and separate approvals. Updates to the plaza could come before anything is decided about the lot.

Where the Parking Terms Get Decided

The response deadline was originally June 17, 2026. Addendum No. 4 moved it to 2 p.m. on Wednesday, July 1, 2026. The city's bid page lists the solicitation as "Open," with the status "Pending Council Award." The RFP lays out the steps from here:

  1. The city's Selection Committee ranks the respondents by qualifications, experience and competence. It may ask some of them for presentations first.
  2. The committee sends its ranking and recommendation to the City Manager and/or City Council for approval.
  3. If the recommendation is accepted, the city tries to negotiate an agreement with the top-ranked respondent. If those talks don't succeed, it moves to the next one on the list.

In its March 17 announcement, the city said top candidates would be presented to Council at public meetings. Those meetings will be the first public look at the parts that matter to anyone who parks downtown, like how many months a year the structure charges, whether weekdays are included, whether covered spaces cost more than $4 for the first two hours, and how resident parking is handled. Each of those terms needs city approval before it goes into a final agreement.

If you're wondering how a project like the Latham Plaza lot could shape day-to-day life downtown, or you just want to talk through what's changing at the beaches, the team at Noah Bailey Group follows these council decisions closely and is glad to talk. Contact Us anytime.

Work With Us

With over 35 years of combined local experience, the Noah Bailey Group provides the trusted, personalized real estate expertise you need to guide you through every step of your buying, selling, or investing journey.

Follow Us on Instagram